The timeline below is taken from page 10 of the Preliminary Plan for the new high school as it appeared on the Board's web site as of August 27, 2004. Link to the PDF file directly here.

Imagine a plan that:

  • has already requested funding from voters on a 6/14/04 ballot without officially telling them where the school will be or how the site will change (many voters voted for a school only later to be surprised by the wrong-headed site the District had in mind)
  • still has no independent traffic study done (only the traffic study done by the Administration's own contractor will be accepted, even though it does not reflect reality and ignores safety issues)
  • still does not have a detailed environmental impact study done
  • still does not have an archaeological study done
  • still has site plans changing day by day
  • will not have a site design finalized and a budget confirmed until 1/12/05

Without these things in place, the Board and the AAPS continues to ignore public input precisely because it is driven by an imagined deadline rather than by proceeding responsibly.

Phase Date
Schematic Design (SD)

 

Site Concept (New HS) Preview 8/11 /04
Building Concept (all facilities) Preview 9/22/04
Schematic Design finalized and Construction Budget confirmed 11/10, now changed to 12/8/04
Design Development (DD)  
Site Design Development Finalized and Budget confirmed 1/12/05
Building Design DevelopmentFinalized and Budget confirmed 2/9/05
Construction Documents (CD)  
Site Bid Packages ** (4) Site Bid Pkgs
Building Bid Package Complete Multiple
Bid and Award  
Site Awards ** 8/11, 1/26, 4/13, Sept/05
Building Awards 5/25, Sept/05